Problem 9 Medium
A construction team was originally scheduled to lay a water pipeline in 18 days. After working for 6 days, two-thirds of the team was reassigned to other tasks. How many total days will it take to complete the pipeline?
- A.
- B.
- C.
- D.
- E.
Answer:E
Let the total work required be "1" unit. The original team's daily work rate is . After working for 6 days, they have completed of the total work. When two-thirds of the team is reassigned, the remaining team's efficiency is reduced to , so their new work rate is . The remaining work to be done is , and at the new work rate, it will take days to complete the remaining work. Therefore, the total time required to complete the pipeline is days.